Meeting documents

  • Meeting of Extraordinary meeting, Overview and Scrutiny Committee, Thursday, 8th November, 2018 6.00 pm (Item 83.)

The Leader of the Cabinet, Cllr Naylor will attend the meeting to explain the reasons behind the Cabinet’s decision as set out in the Cabinet Decision Notice dated 18 October 2018 and to respond to the call-in request in relation to Station Road Car Park, Gerrards Cross. Following this there will be an opportunity for the Committee to ask questions and clarify any issues.

Minutes:

The Leader was then asked to respond to the four call-in points put forward by Members.

 

Point 1

Concerns regarding the business case which were discussed recently at the Resources Policy Advisory Group on 25 September 2018. Two Members at this meeting expressed concern over the assumptions of usage and consequently whether this scheme was a good use of taxpayer’s money.

 

The Leader responded as follows:-

 

When the Resources PAG considered the Gerrards Cross Car Park Business Case report on 25 September 2018 concern was raised that the car park take up assumptions were too optimistic i.e. building up to 85% occupancy by year 3.

 

Business Case Figures are as follows

Cabinet

Report

85% Occupancy by year

3

IER – should be more than borrowing cost

2.73%

Net Present Value – negative is good

£6,535,359

(Surplus) / Loss – negative is good

-£1,273,481

 

He referred to the financial business case which was at Appendix 2B of the agenda.  The key point was that the predicted demand from the parking studies for Gerrards Cross was greater than what this car park would deliver; therefore it was not unreasonable to assume it would have a high level of usage within a reasonable short time frame as there would still be an element of unmet demand.

 

Questions were asked by the Committee to the Leader of the Council and the following points were noted from his responses:-

 

·       The initial costs went up once the final design in the planning application had been agreed, and also the revised timetable for the project which included a year’s delay in construction, which led to cost increases.

·       The return on the investment of £1.2 million would be realised over a 40 year period and at the end of this period the Council would still own the asset and the land.

·       There were other examples of business cases for similar, publicly led projects over a 40 year timeframe for this type of project.

 

Following questions by Councillors Bastiman and Bezzant it was agreed that a written response would be sent out to Members with regard to the following question:-

What will happen with the asset after 40 years and what is the benchmark for Government borrowing for that term?

 

Point Two - Communications and consultation with local residents.

 

The Leader responded as follows:-

 

Two information events were held 31st October 2016 and 21 May 2018.  Both were well represented by the Project team and also well attended by members of the local community. A representative from the Architects Broadway Maylan and Planning consultants Peter Brett associates attended; this included the Client Project Manager and Balfour Beatty who were all there to answer questions for visitors.  Officers and Members also attended.  The public were notified by leaflets to commercial and residential occupiers in Station Road and posters were positioned around the car park and via information on social media and the Council’s website.  Local businesses were contacted and meetings were held with BP Collins, Tesco stores and Waitrose and there was a regular dialogue with the Town Council.  During the statutory planning consultation period there was 330 responses received.

 

Following questions by the Committee, Members noted that Gerrards Cross Town Council supported the car park and the planning application. A Member asked what changes had been made following the communication and consultation period. The Leader reported that as per normal practice, feedback was rigorously examined and taken into account. The feedback for example had influenced some of the external design features of the building.

 

Following a question by Councillor Bezzant, it was agreed that written responses would be provided on the following question:-

With regard to the public consultation in 2016 and 2018 how many people attended and were the public events held over a series of days and times so that people could attend ?

With regard to the leaflet drop what area was covered including the number of houses ?

 

Point Three

Concerns regarding the amount of money being borrowed for the Project and the risks associated with this, should be considered by the Overview and Scrutiny Committee, particularly bearing in mind the possibility of Local Government reorganisation.

 

The Leader responded as follows:-

 

The Business Case Report proposed that the project would be funded by borrowing from the Public Works Loan Board (PWLB).

 

The total amount to be borrowed was equal to the amount required to fund the scheme. The total cost of which has been robustly tested.

 

The Key risks and Mitigation for the project have been considered and were contained in the Cabinet report.

 

Local Government reorganisation had no impact on car parking demand and when local government organisation occurred, both the asset and the loan would transfer to the relevant new organisation. Until the new unitary organisation came into effect South Bucks District Council continued to discharge its duties in terms of addressing future car parking demand.

 

Following questions by the Committee, it was noted that although a decision had been made on having a Unitary District Council, the Council needed to discharge its statutory functions in the usual way. The timetable for a Unitary District Council to be established was 1 April 2020.

 

A discussion then took place on whether a private organisation, who had access to this funding and process would take out a similar investment. The Leader responded that Councils generally perform functions that the private sector would not, as the Council was a public sector organisation providing services to the public. Therefore, it was able to take a view on the public benefit of an investment, whereas private companies purely look at financial return. However, the Cabinet were satisfied that the business case was robust. The Internal Rate of Return which was a metric used to calculate the profitability of potential investments but was not an absolute yardstick for public bodies, Councils could take advantage of favourable loan rates from the Public Works Loan Board which could also be fixed for long durations unlike many commercial loans. In the longer term as the income grew with inflation, but the cost of the loan did not, the development would cover its costs and provide a return to the Council. The payback period would be too long for a commercial operator but the prime purpose of the project was to meet expected parking need

 

Following a question from Councillor Bastiman, it was agreed that a written response would be provided on the following question:-

What information was given to Cabinet with regard to the risk analysis undertaken for the Gerrards Cross Car Park project ?

 

A further question was asked regarding car park charging, with prices rising in regular increments of 50p averaging about 4% a year over the next 40 years and whether the Cabinet had considered different scenarios addressing possible risks. The Leader reported that a sensitivity analysis had been carried out showing the effect on the business case of changing various assumptions. There was a table in the Cabinet report which showed the effect on the Internal Rate of Return, Net Present Value and Profitability figures if some of these assumptions were changed. The Leader was asked if the Cabinet were satisfied with these assumptions and the Leader confirmed that Cabinet was satisfied.

 

 

Point 4

Concerns that the full details of alternative schemes and options have not been fully considered by Members and the reasons for rejecting them e.g. a mixed use scheme would be more appropriate for the locality and proportionate to the actual likely demand for car parking, which could reduce in the future due to new technology. 

  

The Leader responded as follows:-

                                   

Members previously considered a number of alternatives for the car park these included not only varied heights but also a mixed used scheme.  The reduction of the height and a light weight structure was considered in Cabinet in April 2018 but discounted as they as it did not provide enough spaces to meet the predicted car parking demand and the business cases for both were not as beneficial as the one for the development settled upon.   The mixed use scheme was explored early in 2017 and was also dismissed due to the limited number of car parking spaces that would be available after taking into account the parking for the shops and residential premises. 

 

Following a question from Councillor Kelly, it was agreed that a written response be provided to the following question:-

What was the feedback from Members when the alternative options were rejected ?

Supporting documents: